CONTROL OF A THREE LINK UNDERWATER ROBOT

 

MILESTONES AND COMPLETION DATES:

 

Milestone
Intended Completion Date
Knowledge of Manuals
10-Oct
Verifying revolutions
20-Oct
Working with 1 motor
1-Nov
Extending to 3 motors
18-Nov
Progress Report
5-Dec
3 link arm built
20-Jan
PID control testing in underwater tank finished
30-Mar
Abstract and Biography
5-Apr
4-page paper
19-Apr

 

LOG:

Milestone 1: COMPLETED

Milestone 2: COMPLETED

Milestone 3: COMPLETED

Milestone 4: COMPLETED

Milestone 5: COMPLETED

Milestone 6: COMPLETED